Case study · Industrial & energy

Heavy-Duty Power for a Live Energy Site.

Power distribution, heavy-duty containment and certified installation on a working process & energy site, delivered safely, around a live operation, to standard.

Energy / processMerseysideBS7671Live site
FRM's electrical distribution and containment work on a Merseyside process & energy site.Fig. 01 · On site

400 kVA

Power distribution

2,000 m

Cable & containment

100%

Tested & certified

10 wks

On a live site

Client
Energy infrastructure contractor
Sector
Energy / process
Location
Merseyside
Environment
Live industrial site
The environment

An Industrial Site Doesn’t Forgive Shortcuts

Working on a live process & energy site means safety systems, heavy plant and demanding standards, and no room to get the electrical infrastructure wrong.

Safety-Critical

Permit-to-work, isolations and method statements on a live energy site.

Industrial Scale

Heavy plant, long runs and robust containment built for the environment.

Standards-Driven

Installed, tested and certified to BS7671 and the site's own standards.

Tightly Coordinated

Sequenced with the principal contractor and other specialist trades.

Engineering scope

What FRM Engineered and Installed

The full electrical scope, delivered in-house and signed off properly.

01Power distribution

LV distribution, sub-mains and boards out to the process plant.

02Containment & install

Heavy-duty tray, ladder and conduit, routed to suit the environment.

03Controls & interface

Terminations and interfaces for the site's control and monitoring.

04Testing & commissioning

Inspected, tested and commissioned safely within a live site.

05Certification & compliance

Certified to BS7671, working to the site's permit and safety systems.

The outcome

Serious Infrastructure, Delivered Safely and Signed Off

FRM delivered the power distribution and containment a demanding energy site needs, installed safely around a live operation, tested and certified to BS7671, with the records to back it up.

Delivered

On a live site

Certified

To BS7671

Coordinated

With the principal contractor

More work

Related Projects

Galvanised cable tray and containment installed by FRM across a steel-frame ceiling during first-fix.3
Commercial

Cable Containment & First-Fix

Tray, trunking and containment set out properly at first-fix on a large commercial unit.

High-bay LED lighting and power installed by FRM throughout a large industrial unit.4
Industrial

Industrial Unit: Lighting & Power

A full relight and power install in a large unit: high-bay LED throughout.

Got an Industrial or Commercial Project? Get a Free Quote.