Case study · Commercial fit-out

A Working Office, Delivered to Programme.

Office fit-out · Leeds · live environment

Power, data, lighting and certification for a commercial office: designed, installed and tested by one team, coordinated cleanly around the main contractor and handed over on time.

The completed commercial office fit-out by FRM, with feature lighting and clean exposed services.
Delivered to programme
12,000 sq ftFloor area fitted out
120Power & data points
6 wksDelivered to programme
100%Tested & certified
Client
Commercial property firm
Sector
Office / workplace
Location
Leeds
Environment
Live, occupied building
The brief

A Full Electrical Fit-Out, in a Building That Couldn’t Stop

The client needed a complete electrical fit-out for a commercial office, power, data, lighting and the distribution behind it, ready for staff to move in on a fixed date. The catch: the rest of the building stayed live and occupied throughout.

That makes it a coordination job as much as an electrical one. Programme was tight, the main contractor and other trades were working the same floors, and disruption had to be kept to a minimum, all without cutting a corner on the finish or the paperwork.

What we delivered

The Full Electrical Scope, One Accountable Team

Everything from the incoming distribution to the last socket: designed, installed, tested and certified in-house.

Power & Distribution

New sub-mains, distribution boards and small power across the floor.

Data & Comms

Structured cabling and containment, tied back to the comms room.

Lighting & Controls

LED lighting designed for the space, with presence & daylight controls.

Containment & First-Fix

Tray, trunking and conduit set out cleanly, ready for the other trades.

Test & Certification

Inspected, tested and certified to BS7671: paperwork in order.

Trade Coordination

Sequenced around the main contractor and other trades to hold programme.

How it came together

Four Clean Phases, Held to Programme

  1. 01

    Survey & Coordination

    Walked the space, agreed the design and sequenced with the main contractor.

  2. 02

    First Fix

    Containment, cabling and back-boxes installed around the live programme.

  3. 03

    Second Fix & Commissioning

    Accessories, lighting and boards terminated, energised and commissioned.

  4. 04

    Test, Certify & Handover

    Full inspection and testing, certified to BS7671, handed over on time.

The result

Handed Over on Time, Signed Off in Full

A clean, well-finished fit-out delivered without holding up the programme, and certified to BS7671, with the paperwork ready for the building file.

Delivered to programme · zero re-work
FRM just got on with it: tidy, on programme and no surprises. The coordination with the rest of the site was the best we’ve had.
Project manager, main contractor
More work

Related Projects

Galvanised cable tray and containment installed by FRM across a steel-frame ceiling during first-fix.3
Commercial

Cable Containment & First-Fix

Tray, trunking and containment set out properly at first-fix on a large commercial unit.

High-bay LED lighting and power installed by FRM throughout a large industrial unit.4
Industrial

Industrial Unit: Lighting & Power

A full relight and power install in a large unit: high-bay LED throughout.

Planning a Commercial Project? Get a Free Quote.